Piping Installation and Erection Procedure

Advertisement

Piping Installation and Erection Procedure


Piping Installation Procedure:


Piping Installation normally starts after civil supports are erected and major equipment’s are placed in the construction site. The installation of piping can be grouped into the following parts:

  • Pipework Erection
  • Installing Piping Flanges, Valve and equipment Flange Connection
  • Installing pipe Supports
  • Pressure testing
  • Insulation and Painting
  • Marking and Identification
  • Installing Expansion Joints
  • Vents and Drains
  • Underground Pipe Installation

Pipework Erection Procedure:


Advertisement

Proper planning should be made to erect piping, area-wise following piping isometric and GA drawings. The following piping erection guidelines should be followed:

  • All tools, equipment, ropes, and pipes must be inspected and certified by HSE guidelines before erection to ensure that they are safe and ready, and clean and free from loose contamination.
  • Pre-fabricated spools need to be identifiable and numbered/tagged.
  • Pipework should be erected on supports designated for the specific line. Primary pipe supports can be welded prior to erection following pipe support drawings. The number of temporary supports shall be minimized.
  • Undue stresses should not be applied to force the piping to keep in the proper place.
  • To avoid ingress of moisture and foreign matter, pipe openings should be sealed during erection.
  • Installation of piping on pipe racks should be done from lower elevation to higher elevation.
  • Large bore piping shall be installed prior to small-bore piping.
  • Piping Joints shall be properly aligned.
  • Pipe clearances from other pipes, equipment, and structures should be maintained.

Installing Piping Flanges:

Advertisement

  • Clean pipe flanges should be brought up flush and square without forcing to bear uniform bolt tension and gasket compression. Line items like orifice flanges, spectacle blinds, strainers, etc shall be installed following proper orientation. A logical bolt tightening (Hydraulic bolt tensioning & torque tensioning) sequence needs to be followed.

  • The flange connections to this equipment shall be checked for misalignment, excessive gap, etc. Until both side flanges are ready for mating connection, flange covers shall be retained on all flanged connections to the valve or equipment.

  • Extra care to be exercised for flange connections to pumps, turbines, compressors, cold boxes, air coolers, etc. Blanks or spades should be used on equipment to prevent the ingress of internal pipe debris. Bolting shall move freely through accompanying bolt-holes at the right angle to the flange faces and a clear gap between two flange faces for gasket needs to be maintained before gasket installation.

Pipe Support Installation:


  • Relevant pipe support detail drawings should be used for installing pipe supports.
  • Additional stress should not be introduced to fit the supports.
  • The pipe shoe should be installed at the center of the beam without any offset.
  • Where spring supports are required, those should be locked until hydro testing and insulation. Manufacturer installation guidelines should be followed.
  • Where PTFE plates are used for friction reduction, ingress of sand in between SS and PTFE plates should be avoided.
  • Piping to be arranged to facilitate pipe-supporting, and shall be well-planned for ease of removal of equipment for inspection and servicing.

Pressure Testing

  • Following the guidelines, hydrostatic or pneumatic testing should be performed to check the system’s integrity. In case of leakage, those are repaired and re-tested again. 

  • After pressure testing, bare pipes and painted as per specification. High temperature lines are insulated following the insulation procedure.
Marking and Identification:

  • All pipes and fabricated fittings are marked on their outside with letters and numbers for easy identification of lines, their services, etc. Marking is normally done by stamping, tagging, stenciling, or using any other permanent marking method.

Installation of Expansion Joints:

  • Expansion joints are normally required for critical piping systems. Bellows should be installed following the vendor’s guidelines and installation drawings. Piping should be perfectly aligned with the expansion joint as mentioned in the detailed drawings.

Vents and Drains:

  • Ideally vents and drains should be located in the isometric drawing or GA drawings. In case, high point vents and low point drains are not provided in those drawings, these should be provided as per the instructions of Engineer-in-Charge/Job standards/ Piping Specifications.

Installing Underground Pipes

  • Before starting buried pipe installation, it must be ensured that trench excavation is done following the approved drawing.
  • Final measurement, Tests, and surveys to be completed prior to backfilling.
  • Depth of cover as mentioned in the GA drawings should be maintained.

Equipment and Tools for Pipe Erection

Advertisement

The following equipment and tools are used for piping erection and installation purposes.

  • Welder’s gauge
  • Pipefitters square
  • Fitter grips
  • Centering head
  • Flange aligners
  • Pipe wraps
  • Pipe clamps
  • Pipe cutter
  • Pipe stands
  • Water hose
  • Welding machine
  • A-frame
  • Adjustable wrench
  • C clamp
  • Centre punch
  • Chain block
  • Forklift
  • Steel tape
  • Tower crane
  • Boom lifter
  • Cranes
  • Spanners and Torque Wrenches

Safety during Piping Installation


Advertisement

“SAFETY FIRST” is the primary concern of engineers. Hence, the safety of the people should override all other targets and achievements. Any unsafe situation should immediately be reported to the HSE manager and the working should be postponed. So the following guidelines should always be observed during piping installation and erection.

  • Identifying the hazards associated with piping services. This is mainly concerned while working in operating plants.
  • Understanding the color codes: Pipes are normally colored following standard guidelines to identify based on fluid service categories. The following image (Fig. 2) provides a sample color-coding table based on BS 1710 standard.
  • Exercise extra care while tying a pipe into an operating system.
  • Use proper safety guidelines while working at heights and confined spaces.
  • Always be aware of what can go wrong and what to do if things go wrong.
  • Personal safety equipment must always be carried.